Project management is a combination of various activities such as planning, organizing, implementing, controlling and monitoring. It allows the companies to plan their works by using limited resources. In this, it is project manager responsibilities to clearly state objectives and deliverables of the work so that a project plan can be developed in right manner. The present report is based on Fundamental of Project Management and to understand this, a case of ProjectPlus is taking into the consideration. Company delivers several project management services to its business clients such as Project Planning, Project Reporting, Risk Management, Benefits Realisation, providing teams of professionals to manage projects on behalf of clients etc. In the current time, there are three companies who comes contact with ProjectPlus in order to getting the help in launching of new products in UK by organizing an event on 2nd January 2017 (Kerzner, 2013).
On the basis of the given case scenario, it has evidence that Tesla Motors, GE Healthcare and DropBox are the three companies which has contacted to ProjectPlus to launch their new products and services in the marketplace. These business clients have deal in various industries and they have healthcare, automotive and cloud computing technology.
ProjectPlus Company has chosen the product launch event of DropBox where the business client wants to introduce a new encryption functionality service to their enterprise plan customers. With the help of this, it will become easy for DropBox service users to store highly sensitive data files, their sharing and transfer. The purpose and outcomes for business client of ProjectPlus by organizing the lunching event of a product in the UK are as follow:
Project objectives define as the outcomes of the project which are long, medium or short team. It should be related to scope of project plan because it directly affects deliverables of work. By considering the major outcomes of the project, the project manager develops some project objectives. In the context of launching of new product of Dropbox, few SMART objectives have prepared. The reason of stating some SMART objectives because it will set few limitations in front of the project manager that will help in attaining the major deliverables of project work in a right manner. Along with this, this will help in comparing actual results with the expected outcomes where monitoring process of project plan becomes easier. By this, project manager will determine some unmet objectives and the reasons behind not completion of SMART objectives so that in the future such kinds of mistakes cannot be carried out. Hence, SMART objectives in the context of launch event project of Dropbox are as follows:
On the basis of the given case scenario, it has clearly identified that Dropbox has needed the help of ProjectPlus in launching of new product in the UK. To create a project plan, project manager has required developing a project scope including project boundaries, deliverables and requirements. This can be considered as the first section of project planning which has developed on the basis of objectives and major deliverables. For new product launch event, the project scope is as follows:
The new service of Dropbox will facilitate service users to store highly sensitive data files, their sharing and transfer. The new encryption functionality service will keep secure the information of its business clients from any kind of cyber crime. The following event will explain various benefits of new services of Dropbox to the audience so that they can influence the customer to buy new cloud computing services.
Rather than this, project boundaries are a part of project scope where different characteristics of project plan can be measured and evaluated. Along with this, it states various things such as what areas should be included and what elements should not be included in plan. It helps the project manager to stated main deliverables and objectives of plan in clear words. In the support of new product launch event, project boundaries are as follows:
On the basis of SMART objectives, project goals, milestones and its related sub activities, features of new service of Dropbox, interest of stakeholders, roles and responsibilities, major deliverables, client satisfaction level and project scope.
There will some project exclusion criteria will consider at the time of launching of new product of Dropbox in the UK which are as follows:
Project budget is an authorized financial amount that is used to carry out activities of project plan by the project manager. It is a detailed estimation of all kind of costing that needed to complete project plan (Walker, 2015). This prepares at the initial stage of project planning phase by project manager. The given case study evidence that DropBox has approved £150,000 to ProjectPlus for new product launch event which is ,going to be happen on 2nd January 2017 in London. For launching of DropBox new product event, Project Manager of ProjectPlus has estimated a budget which is as follows:
Elements |
Cost in £ |
Human resources |
 |
Consultant 1 (C1) |
2400 |
Consultant 2 (C2) |
2400 |
Consultant 3 (C3) |
2400 |
Consultant 4 (C4) |
2400 |
Consultant 5 (C5) |
2400 |
Consultant 6 (C6) |
2400 |
Searching and booking venue in Auditorium at The Crystal, London for product launch |
7500 |
Placing ads in different kinds of media information sources  |
3000 |
Live Broadcasting of entire product launch event on Internet |
50000 |
Arrangement and selection of catering services |
3500 |
Event execution logistic requirements such as registration, crowd control, health and safety etc. |
5500 |
Promoting event by various sources |
3000 |
Make arrangements of sound and lighting facilities |
5700 |
Transportation of staff |
2800 |
Preparing and sending invitations to the VIP guests |
750 |
Some other Miscellaneous expenses |
9500 |
ProjectPlus service fee |
25000 |
Other Overhead costs |
19350 |
Total |
130,650 |
Project scheduling is one of the most essential aspects of the project management. It helps the project manager to arrange the activities of a project plan according to priorities so that wok can complete within the assign and available resources. If activities not arrange in a right manner or not scheduled as per the requirements than it may be possible that it can create hamper in the success of project (De Bakker, Boonstra and Wortmann, 2010). By considering the case of new product launch event of Dropbox which is conducting by ProjectPlus in London, it becomes important for the project manager to make a right scheduling of project. In this, a particular time frame allocate to each activity so that progress of plan can be tracked. In order to carry out new product launch event, a systematic project scheduling is giving in below table.
Task Name |
Duration |
Start |
Finish |
DropBox product launch project |
24 days |
Wed 11/30/16 |
Mon 1/2/17 |
   Planning |
9 days |
Wed 11/30/16 |
Mon 12/12/16 |
      Market assessment |
3 days |
Wed 11/30/16 |
Fri 12/2/16 |
      Identification of DropBox needs related to new product launch event |
2 days |
Mon 12/5/16 |
Tue 12/6/16 |
      Looking for vendor for catering facility |
2 days |
Wed 12/7/16 |
Thu 12/8/16 |
      Preparing project team |
2 days |
Fri 12/9/16 |
Mon 12/12/16 |
   Executing |
6 days |
Fri 12/9/16 |
Fri 12/16/16 |
      Scheduling activities for project plan |
3 days |
Fri 12/9/16 |
Tue 12/13/16 |
      Booking venue in London as per the number of expected guests |
1 day |
Tue 12/13/16 |
Tue 12/13/16 |
      Selecting catering vendor |
2 days |
Wed 12/14/16 |
Thu 12/15/16 |
      Inform Dropbox about the project plan progress |
3 days |
Wed 12/14/16 |
Fri 12/16/16 |
   Monitoring |
6 days |
Mon 12/19/16 |
Mon 12/26/16 |
      Establishing and maintaining contractual relationship with suppliers |
3 days |
Mon 12/19/16 |
Wed 12/21/16 |
      Project plan review |
2 days |
Thu 12/22/16 |
Fri 12/23/16 |
      Implement correcting activities |
1 day |
Mon 12/26/16 |
Mon 12/26/16 |
   Project closure |
5 days |
Tue 12/27/16 |
Mon 1/2/17 |
      Obtaining feedback from business client |
2 days |
Tue 12/27/16 |
Wed 12/28/16 |
      Closing of contracts |
2 days |
Thu 12/29/16 |
Fri 12/30/16 |
      Project sign off |
1 day |
Mon 1/2/17 |
Mon 1/2/17 |
Task Name |
Duration |
Start |
Finish |
Predecessors |
DropBox product launch project |
24 days |
Wed 11/30/16 |
Mon 1/2/17 |
 |
   Planning |
9 days |
Wed 11/30/16 |
Mon 12/12/16 |
 |
      Market assessment |
3 days |
Wed 11/30/16 |
Fri 12/2/16 |
 |
      Identification of DropBox needs related to new product launch event |
2 days |
Mon 12/5/16 |
Tue 12/6/16 |
3 |
      Looking for vendor for catering facility |
2 days |
Wed 12/7/16 |
Thu 12/8/16 |
4 |
      Preparing project team |
2 days |
Fri 12/9/16 |
Mon 12/12/16 |
5 |
   Executing |
6 days |
Fri 12/9/16 |
Fri 12/16/16 |
 |
      Scheduling activities for project plan |
3 days |
Fri 12/9/16 |
Tue 12/13/16 |
5 |
      Booking venue in London as per the number of expected guests |
1 day |
Tue 12/13/16 |
Tue 12/13/16 |
6 |
      Selecting catering vendor |
2 days |
Wed 12/14/16 |
Thu 12/15/16 |
8 |
      Inform Dropbox about the project plan progress |
3 days |
Wed 12/14/16 |
Fri 12/16/16 |
9 |
   Monitoring |
6 days |
Mon 12/19/16 |
Mon 12/26/16 |
 |
      Establishing and maintaining contractual relationship with suppliers |
3 days |
Mon 12/19/16 |
Wed 12/21/16 |
10,11 |
      Project plan review |
2 days |
Thu 12/22/16 |
Fri 12/23/16 |
13 |
      Implement correcting activities |
1 day |
Mon 12/26/16 |
Mon 12/26/16 |
14 |
   Project closure |
5 days |
Tue 12/27/16 |
Mon 1/2/17 |
 |
      Obtaining feedback from business client |
2 days |
Tue 12/27/16 |
Wed 12/28/16 |
15 |
      Closing of contracts |
2 days |
Thu 12/29/16 |
Fri 12/30/16 |
17 |
      Project sign off |
1 day |
Mon 1/2/17 |
Mon 1/2/17 |
18 |
Gantt Chart:
Network Diagram:
Key milestones
Key milestones |
Expected date of start and completion |
|
DropBox product launch project |
Wed 11/30/16 |
Mon 1/2/17 |
   Planning |
Wed 11/30/16 |
Mon 12/12/16 |
   Executing |
Fri 12/9/16 |
Fri 12/16/16 |
   Monitoring |
Mon 12/19/16 |
Mon 12/26/16 |
   Project closure |
Tue 12/27/16 |
Mon 1/2/17 |
Â
Work Breakdown Structure:
Â
In Dropbox new product launch, it has included various project stakeholders. These have contained different interest and perceptions and it has varied as per their expectations and needs. With the aim of analyzing the role of project stakeholders in the following project, Project Stakeholder Analysis is taking into the consideration by using RACI matrix (Jun, Qiuzhen and Qingguo, 2011). On the basis this, responsibility, accountability, consulted and informed of six different stakeholders is as follows:
Task |
Project Manager i.e. C1 |
C2 |
C3 |
C4 |
C5 |
C6 |
Market assessment |
A, R |
I |
I |
I |
 |
 |
Identification of DropBox needs related to new product launch event |
A, R |
 |
 |
 |
 R |
 |
Looking for vendor for catering facility |
A,R |
C |
C |
C |
 |
 |
Preparing project team |
I |
I |
C |
A,R |
 |
 |
Scheduling activities for project plan |
A, C |
R |
C |
I |
 |
 C |
Booking venue in London as per the number of expected guests |
A, R |
C |
C |
I |
 |
 |
Selecting catering vendor |
I |
C |
A |
 |
 |
R |
 Inform Dropbox about the project plan progress |
I |
A,R |
 |
 |
 |
 |
Establishing and maintaining contractual relationship with suppliers |
A, I |
 |
R |
 |
C |
 |
Project plan review |
I |
 |
A |
 |
R |
 R |
Implement correcting activities |
A |
 |
 |
R |
I |
 I |
Obtaining feedback from business client |
A, R |
 |
 |
 |
 |
 |
Closing of contracts |
A,C |
C |
C |
C |
 |
 |
Project sign off |
A |
R |
R |
R |
R |
I |
8. Assessment of project procurement strategies
Project procurement is a process which is using by the organizations in the present time to attain business objectives. It is completely different from the other kinds of procurement methods. This depends over goals and objectives of the project which is important for the success of the plan. So, it becomes essential that procurement activities should be planned and implemented in systematic manner because it ensures that whether the proposed project deliver the expected outcomes or not after the completion (Caniëls and Bakens, 2012). In the case of Dropbox new service launch event, it has determined from the case study that there are some activities which has not handled by ProjectPlus. For this, company has decided to outsource it so that it becomes easy for project manager to focus over main aim. The related outsourced tasks have lightning, sounds, catering, decoration, booking of place in London etc. In order effectively complete all these activities, ProjectPlus has to look toward vendors or suppliers that can able to carry out outsourcing activities. For this, the cited firm has to considered project procurement strategy i.e. Vendor Rating Technique. First stage of this method is determining those works in the project plan which actually needed to be outsourced. This is called plan procurement phase of suggested technique. In second phase, conduct procurement process carries out where ProjectPlus has put the ads in various sources to invite the vendors for the bid. Next step is Administer Procurements where organization has established the short term relationship with the suppliers so that a right vendor can be selected which should be under the budget of ProjectPlus. Last stage of Vendor Rating Technique has Close Procurements where firm has closed contracts with the suppliers after completion of Dropbox new product launch event. From the above assessment process of project procurement strategy, it has found that Vendor Rating Technique has effectively helped ProjectPlus to select the right vendor for outsourcing activities.
The last but most important thing in a project is occurring of different types of risks. A project is carrying out within the limited resources and takes the advantages of opportunities. With the help of Project Risk Management plan, an effective and appropriate risk management can be carried out by the project manager (Artto, Kulvik, Poskela and Turkulainen, 2011). In the context of DropBox new service launch event, probability of occurrence of uncertainties that may impact over the project objectives have high. For this, a complete and systematic risk assessment process with the help of risk resister can be carried out.
Attached in Excel sheet
From the above study, it can be concluded that project management ha s widely used by many of the organizations to carry out their various business projects in effective manner. It has assisted in prepared the project plan with the help of different sets of activities such as planning, organizing, implementing, monitoring etc. In the present study, ProjectPlus has developed project plan for Dropbox because business client want to launch its new service in the UK market. There have various project SMART objectives developed to attain the major deliverables of the plan. Along with this, project scope with excluding and including criteria has defined. The entire launching event has completed within the given budget and time limitations. On the other hand, stakeholder analysis process has carried out to determine their different roles in Dropbox new product launch event.
The present study has a management consultancy report where statement has prepared on DropBox Company which has contacted to ProjectPlus for its new product launch. From this work, I have learned various things which have helped me in the future. In this context, first thing which I have understood is defining project scope. Under this, I have gained knowledge about who to define a project scope, what things should be considered or excluded in this process etc. Before doing this project, I had not enough knowledge about project scope but after completion of this work, I have learned several things regarding this. It will help me in future to define a scope of any type of project. Along with this, I will state major deliverables with including and excluding criteria. On the other hand, I have increased my knowledge regarding SMART objectives in which I have learned that how to define objectives of a plan in logical manner. Â In the near future, the same knowledge will apply by me to develop SMART objectives for project plan so that it can be used as key performance indicators to compare expected and real outcomes and find the issues of deviations.
Beside this, from the following study, I have learned about various stages of project management. It has contained some steps such as initial, planning, organizing, implementing. Monitoring and controlling as well as closing. With the help of these phases, a project plan can be easily developed which has helped in effective execution of work. On the basis of this, the progress of plan has monitored and managed with the time. This knowledge has allowed me in the future to develop a project plan on any topic so that I can manage whole project in an appropriate manner. Along with this, it will assist me to complete the assign activities as per the planned activities. While, the current research has helped me to gain the knowledge about Work Breakdown Structure. From this, I have learnt that how to divide a whole work into small manageable sections so that within the assign specific timeframes, entire plan can be completed. In the near future, I can utilize the following information and divided the long and complex projects in various small manageable sections and carry out plan steps by steps. Â
From the current research, I have gained the knowledge about what is the project budget and how it creates to effective utilization of available funds. In the study, I have determined that how a project manager considers present costs of activities and developed a budget for the project plan. The information gain from this will assist me in the future to prepare and allocate budge to various activities of project plan. With the application of different budget allocation techniques, I will optimally utilize available funds and keep control over the expenses so that plan can be run within the budget not on over budget. On the other side, I have learned the knowledge regarding stakeholder analysis to determine their interest in a project plan. With the help of this, I have gained the information that how one stakeholder interest and power has different from the other ones. In addition to this, I have understood about the application of RACI matrix in stakeholder analysis within the context of planned project. This gain knowledge will help in future regarding analysis of stakeholdersâ interest in the projects in effective manner by using RACI matrix.
Apart from this, the following research has assisted me to gain the understanding regarding scheduling of a project and development of plan. It has also helped me to know what the milestones are in project plan and how it has created or set during planning. This information will lead my career in future in new direction where I will able to develop a project plan for any project and assign milestones with right scheduling. Further, I will able to allocate the resources as well as budget for planned activities so that work can be carried as per the set action plan and complete it within in given constraints. On the other hand, last but not least which I have learned from the present study is how to use MS project for various activities of project plan. With the help of this, I have learned how to schedule activities, preparing Gantt Chart and network diagram etc. In the upcoming future, I will use this skill to develop various project plans with the application of MS Project software. Hence, from the overall study, it has reflected that I have learned several things that will help me in future to move my career in Project Management and Operation area.
To export references to this Sample, select the desired referencing style below:
Global Assignment Help Australia ,(2024),https://au1.globalassignmenthelp.com.au/free-samples/management-assignment-help/bmt-7073-fundamentals-of-project-management-level-5
Global Assignment Help Australia (2024) [Online]. Retrieved from: https://au1.globalassignmenthelp.com.au/free-samples/management-assignment-help/bmt-7073-fundamentals-of-project-management-level-5
Global Assignment Help Australia. (Global Assignment Help Australia, 2024) https://au1.globalassignmenthelp.com.au/free-samples/management-assignment-help/bmt-7073-fundamentals-of-project-management-level-5
Global Assignment Help Australia. [Internet]. Global Assignment Help Australia.(2024), Retrieved from: https://au1.globalassignmenthelp.com.au/free-samples/management-assignment-help/bmt-7073-fundamentals-of-project-management-level-5
Students sometimes cannot express their inability to work on assignments and wonder, "Who will do my assignment?" To help them understand the complexities of writing, we are providing "samples" on various subjects. Also, we have experienced assignment writers who can provide the best and affordable assignment writing services, essay writing services, dissertation writing services, and so on. Thus, don't wait any longer! Place your order now to take advantage of discounted deals and offers.
Limited Time Offer
Exclusive Library Membership + FREE Wallet Balance
1 Month Access !
5000 Student Samples
+10,000 Answers by Experts
Get $300 Now
Update your Number